Project - Detail Implementation Schedule |
|
|
|
|
|
(items
in italics have been completed) |
|
Start |
End |
Description |
|
rev: 9/18/09 |
9/16/08 |
9/16/08 |
SQL Server and EX software install |
|
9/17/08 |
9/18/08 |
Orientation Training |
|
|
10/14/08 |
10/15/08 |
Pre-conversion Assessment (Data Mapping) |
|
|
|
|
|
|
Trip #1 Pre-configuration |
|
11/18/08 |
11/21/08 |
Business Modules (G/L,A/P,A/R, Purchasing, Fixed
Assets) |
11/18/08 |
11/21/08 |
Human Resources modules (Payroll, Personnel) |
|
11/24/08 |
11/24/08 |
Common Module (All module managers attend this
training) |
11/25/08 |
11/26/08 |
Admissions, Financial Aid Manager, PowerFAIDS
modules |
12/2/08 |
12/4/08 |
Registration/Advising/Student Life Modules |
|
|
11/4/08 |
TLU delivers initial data extract |
|
|
|
|
1/16/09 |
Jenzabar delivers initial data conversion mapping
document |
|
1/23/09 |
TLU delivers all configuration worksheets |
|
|
|
|
Trip #2 Configuration Review and
Training |
|
2/10/09 |
2/13/09 |
Business Modules (G/L,A/P,A/R, Purchasing, Fixed
Assets) |
2/10/09 |
2/13/09 |
Human Resources modules (Payroll, Personnel) |
|
2/16/09 |
2/20/09 |
Admissions, Financial Aid Manager, PowerFAIDS
modules |
2/16/09 |
2/20/09 |
Registration/Advising/Student Life Modules |
|
3/3/09 |
3/4/09 |
Data Mapping review (change from original schedule) |
|
|
|
|
|
|
3/1/09 |
PowerFaids operational for shadow processing by
Financial Aid |
|
3/13/09 |
Jenzabar delivers final mapping and data conversion
contract |
|
3/27/09 |
TLU approves data conversion contract |
|
|
4/1/09 |
Jenzabar/TLU
work on data conversion |
|
|
4/6/09 |
EX security training for IT - Gus Ortiz |
|
|
4/7/09 |
Mid-term project review w/Gus Ortiz |
|
|
4/17/09 |
Jenzabar provides scripts for finance data |
|
|
4/17/09 |
TLU posts data for module mgr review |
|
4/20/09 |
4/24/09 |
TLU processes first pass data conversion |
|
4/27/09 |
4/29/09 |
JICS Portal technical training for IT |
|
4/30/09 |
5/1/09 |
First pass data validation (TLU) |
|
|
|
|
Trip #3 Basic Module Training |
|
5/4/09 |
5/4/09 |
Common Module (All Module Managers attend this
session) |
5/5/09 |
5/8/09 |
Admissions, Financial Aid Manager, and PowerFAIDS
(AD/FAM/PF) |
5/12/09 |
5/15/09 |
Registration/Advising/Student Life (RE/AV/SA)
Modules |
5/19/09 |
5/22/09 |
Business Modules (G/L, A/P/ A/R, Purchasing, Fixed
Assets) |
5/21/09 |
5/22/09 |
Human Resources modules (Payroll, Personnel) |
|
|
|
5/21/09 |
7/31/09 |
Begin work on external system interfaces
(Library/EMS/RE/CBORD/DSX) |
5/27/09 |
5/30/09 |
Jenzabar Annual Meeting - Washington DC |
|
|
6/1/09 |
Final Production Server Hardware ordered (Dell) |
|
|
|
|
|
Trip #4 Advanced Module Training |
|
6/9/09 |
6/12/09 |
Admissions, Financial Aid Manager, and PowerFAIDS
(AD/FAM/PF) |
6/15/09 |
6/19/09 |
Registration/Advising/Student Life (RE/AV/SA)
Modules |
6/23/09 |
6/26/09 |
Business Modules (G/L, A/P/ A/R, Purchasing, Fixed
Assets) |
6/25/09 |
6/26/09 |
Human Resources modules (Payroll, Personnel) |
|
|
|
|
7/31/09 |
Financial Aid Certifies Student Loans on PowerFaids |
|
7/6/09 |
7/10/09 |
Portal CRM training for module managers
(student/faculty portlets) |
|
|
7/14/09 |
7/17/09 |
Basic InfoMaker Training (12 seat
limit for report writers) - section 1 |
7/20/09 |
7/23/09 |
Basic InfoMaker Training (12 seat limit for report
writers) - section 2 |
8/4/06 |
8/6/06 |
Process and Data Validation Consulting |
|
7/20/09 |
9/15/09 |
Final Production Hardware installed & on-line |
|
|
10/15/09 |
external system interfaces completed |
|
10/15/09 |
10/30/09 |
portal setup with online
payment merchant |
|
|
8/31/09 |
Primary Data Validation
complete |
|
8/17/09 |
8/28/09 |
Project Quiet time - Fall '09 start |
|
|
9/25/09 |
Portal CRM setup for
staff portlets |
|
|
10/4/09 |
All process and data validations delivered to
Jenzabar |
|
|
Go-live confirmation |
|
9/4/09 |
10/2/09 |
Portal "look &
feel" setup & approvals |
|
9/15/09 |
10/2/09 |
Final testing of external interfaces
(Library/EMS/RE/CBORD/DSX) |
9/30/09 |
10/30/09 |
Portal awareness
"marketing" begins for students/staff etc |
9/25/09 |
10/2/09 |
Refresher training for
administrative offices |
|
10/15/09 |
10/30/09 |
Portal training workshops for TLU faculty |
|
|
10/2/09 |
Final security pass on
access |
|
|
10/9/09 |
TLU posts final pass of data to Jenzabar |
|
|
10/9/09 |
Financial Aid PowerFaids in production |
|
10/12/09 |
10/16/09 |
Jenzabar Go-Live consulting (on-site) |
|
|
|
10/17/09 |
11/6/09 |
Portal training for TLU students "drop-in" workshops |
|
12/8/09 |
12/11/09 |
Intermediate InfoMaker Report writer training |
11/16/09 |
12/7/09 |
Portal training for general TLU staff |
|
|
|
|
12/1/09 |
7/15/10 |
Begin Development conversion to Jenzabar |
|
|
1/15/10 |
2/28/10 |
Executive Dashboard setups |
|
|
|
4/30/10 |
Complete 2009-10 academic
catalog scribing for advising |
|
|
|
6/7/10 |
6/11/10 |
Development module
"go-live" |
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|