Jenzabar Project - Detail Implementation Schedule 
(items in italics have been completed)
Start End Description rev: 9/18/09
9/16/08 9/16/08 SQL Server and EX software install
9/17/08 9/18/08 Orientation Training
10/14/08 10/15/08 Pre-conversion Assessment (Data Mapping)
Trip #1 Pre-configuration
11/18/08 11/21/08 Business Modules (G/L,A/P,A/R, Purchasing, Fixed Assets)
11/18/08 11/21/08 Human Resources modules (Payroll, Personnel)
11/24/08 11/24/08 Common Module (All module managers attend this training)
11/25/08 11/26/08 Admissions, Financial Aid Manager, PowerFAIDS modules
12/2/08 12/4/08 Registration/Advising/Student Life Modules
11/4/08 TLU delivers initial data extract
1/16/09 Jenzabar delivers initial data conversion mapping document
1/23/09 TLU delivers all configuration worksheets
Trip #2 Configuration Review and Training
2/10/09 2/13/09 Business Modules (G/L,A/P,A/R, Purchasing, Fixed Assets)
2/10/09 2/13/09 Human Resources modules (Payroll, Personnel)
2/16/09 2/20/09 Admissions, Financial Aid Manager, PowerFAIDS modules
2/16/09 2/20/09 Registration/Advising/Student Life Modules
3/3/09 3/4/09 Data Mapping review (change from original schedule)
3/1/09 PowerFaids operational for shadow processing by Financial Aid
3/13/09 Jenzabar delivers final mapping and data conversion contract
3/27/09 TLU approves data conversion contract
4/1/09 Jenzabar/TLU  work on data conversion
4/6/09 EX security training for IT - Gus Ortiz
4/7/09 Mid-term project review w/Gus Ortiz
4/17/09 Jenzabar provides scripts for finance data 
4/17/09 TLU posts data for module mgr review
4/20/09 4/24/09 TLU processes first pass data conversion
4/27/09 4/29/09 JICS Portal technical training for IT
4/30/09 5/1/09 First pass data validation (TLU)
Trip #3 Basic Module Training
5/4/09 5/4/09 Common Module (All Module Managers attend this session)
5/5/09 5/8/09 Admissions, Financial Aid Manager, and PowerFAIDS (AD/FAM/PF) 
5/12/09 5/15/09 Registration/Advising/Student Life (RE/AV/SA) Modules
5/19/09 5/22/09 Business Modules (G/L, A/P/ A/R, Purchasing, Fixed Assets) 
5/21/09 5/22/09 Human Resources modules (Payroll, Personnel)
5/21/09 7/31/09 Begin work on external system interfaces (Library/EMS/RE/CBORD/DSX)
5/27/09 5/30/09 Jenzabar Annual Meeting - Washington DC
6/1/09 Final Production Server Hardware ordered (Dell)
Trip #4 Advanced Module Training
6/9/09 6/12/09 Admissions, Financial Aid Manager, and PowerFAIDS (AD/FAM/PF) 
6/15/09 6/19/09 Registration/Advising/Student Life (RE/AV/SA) Modules
6/23/09 6/26/09 Business Modules (G/L, A/P/ A/R, Purchasing, Fixed Assets) 
6/25/09 6/26/09 Human Resources modules (Payroll, Personnel)
7/31/09 Financial Aid Certifies Student Loans on PowerFaids
7/6/09 7/10/09 Portal CRM training for module managers (student/faculty portlets)
7/14/09 7/17/09 Basic InfoMaker Training (12 seat limit for report writers) - section 1
7/20/09 7/23/09 Basic InfoMaker Training (12 seat limit for report writers) - section 2
8/4/06 8/6/06 Process and Data Validation Consulting
7/20/09 9/15/09 Final Production Hardware installed & on-line
10/15/09 external system interfaces completed
10/15/09 10/30/09 portal setup with online payment merchant
8/31/09 Primary Data Validation complete
8/17/09 8/28/09 Project Quiet time - Fall '09 start
9/25/09 Portal CRM setup for staff portlets
10/4/09 All process and data validations delivered to Jenzabar
Go-live confirmation
9/4/09 10/2/09 Portal "look & feel" setup & approvals
9/15/09 10/2/09 Final testing of external interfaces (Library/EMS/RE/CBORD/DSX)
9/30/09 10/30/09 Portal awareness "marketing" begins for students/staff etc
9/25/09 10/2/09 Refresher training for administrative offices
10/15/09 10/30/09 Portal training workshops for TLU faculty
10/2/09 Final security pass on access
10/9/09 TLU posts final pass of data to Jenzabar
10/9/09 Financial Aid PowerFaids in production
10/12/09 10/16/09 Jenzabar Go-Live consulting (on-site)
10/17/09 11/6/09 Portal training for TLU  students "drop-in" workshops
12/8/09 12/11/09 Intermediate InfoMaker Report writer training
11/16/09 12/7/09 Portal training for general TLU staff
12/1/09 7/15/10 Begin Development conversion to Jenzabar
1/15/10 2/28/10 Executive Dashboard setups
4/30/10 Complete 2009-10 academic catalog scribing for advising
6/7/10 6/11/10 Development module "go-live"